Preparatory work to begin the main stage of construction is ongoing at the future site of Kambarata Hydropower Plant-1 (HPP-1). The press service of the Ministry of Energy of Kyrgyzstan reported.
As of now, significant progress has been made on key infrastructure components:
A transportation tunnel has been constructed to safely deliver equipment and building materials.
70 percent of new access roads to the dam and construction sites have been completed.
60 percent of work on tunnel ventilation, lighting systems, and internal road concreting has been completed.
60 percent of the 110 kV transmission line and 110/6 kV substation — which will supply electricity to the construction facilities — has been built.
40 percent of the shift camp for workers and specialists has been constructed.
19–20 percent of the bridge across Naryn River, which will provide access to the hydropower plant building, has been completed.